TCN Effects Maintenance On Eight Towers Along Zaria–Funtua 132kV Line Without Disrupting Transmission

Published

on

 

The Transmission Company of Nigeria (TCN), Kaduna Region, has successfully carried out live-line maintenance on the Zaria–Funtua 132kV Transmission Line without disrupting bulk power transmission.

 

TCN General Manager, Public Affairs, Ndidi Mbah disclosed this in a statement, explaining that the maintenance was carried out while the towers were under energized conditions without carrying out planned power outage.

 

“The maintenance exercise was carried out by TCN’s Live-Line Crew from Saturday, July 4 to Tuesday, July 7, 2026. It involved the replacement of damaged glass disc insulators on selected transmission towers with a combination of polymer and glass disc insulators to restore the integrity and reliability of the insulation strings.

 

“The affected towers included T14, T17, T40, T63, T78, T175, T177 and T178, each of which had at least five damaged glass disc insulators.

 

“The maintenance was successfully executed under energized (live-line) conditions, eliminating the need for a planned outage while ensuring the uninterrupted transmission of bulk electricity throughout the exercise”, she stated.

 

Mbah noted that the successful completion of the exercise underscores TCN’s commitment to maintaining a safe, reliable and efficient transmission network through the deployment of modern live-line maintenance techniques.

 

Advertisement
Click to comment

Leave a Reply

Your email address will not be published. Required fields are marked *

RENEWED HOPE AGENDA

HAPPY BIRTHDAY

Our Naira Our Pride

NNPC: WE ARE HIRING

THE RENEWED HOPE AGENDA

ADVERTISEMENT

PRESS RELEASE

Click to read full text


CAVEAT EMPTOR

Advertisement

CBN Advert

Click the link to visit
Advertisement
Advertisement
Advertisement

Happy New Year

Facebook

Advertisement
Advertisement

Breaking News...