FG Injects 416MW Into North-East Grid as Gombe Power Capacity Doubles, 70,000 More Homes to Benefit

Published

on

 

By Clement Nwoji

 

The Federal Government on Thursday commissioned a new 120MVA transmission substation in Billiri and upgraded the Gombe Transmission Substation with new 300MVA and 100MVA transformers, delivering a combined additional 416MW of electricity capacity to the North-East power network.

The projects, commissioned by Minister of Power, Joseph Tegbe, add 240MW at the 330kV transmission level and another 176MW at the 132kV level, significantly increasing the region’s ability to receive and distribute electricity.

A major highlight of the investment is the doubling of transmission capacity at the Gombe Transmission Substation from 300MVA to 600MVA, alongside an upgrade that is expected to improve electricity supply to more than 70,000 additional households across Gombe and neighbouring parts of the North-East, including Yobe State.

Speaking during the commissioning, Tegbe said the new Billiri Substation, equipped with two 60MVA transformers and connected to the Gombe-Zabana-Yola transmission line, was designed to break longstanding electricity constraints limiting economic activities in Billiri, Numan and surrounding communities.

He said reliable electricity remains critical to attracting investment, supporting businesses and creating jobs, adding that the projects reflect President Bola Tinubu’s commitment to expanding critical infrastructure and ensuring communities are not denied economic opportunities because of inadequate power supply.

Tegbe also appealed to residents to safeguard the installations against vandalism, describing the facilities as community assets built for their benefit.

Gombe State Governor Muhammadu Inuwa Yahaya, represented by Commissioner for Energy and Mineral Resources Sanusi Ahmed Pindiga, said the projects would strengthen electricity access across host communities and adjoining states while supporting economic growth.

The traditional ruler of Tangale Chiefdom and Seriki of Billiri, Alhaji Danladi Sanusi Dalandi, said improved electricity would boost businesses, healthcare services, education and employment opportunities in the area.

At the Gombe Transmission Substation, the minister commissioned a new 300MVA, 330/132kV transformer and a 100MVA, 132/33kV transformer, replacing an existing 30MVA unit and raising downstream capacity to 220MVA.

Managing Director of the Transmission Company of Nigeria (TCN), Sule Ahmed Abdulaziz, said electricity demand in Gombe had outgrown the station’s former capacity, necessitating the upgrade.

He noted that the project, awarded in June 2021 and completed in June 2026, would provide greater flexibility for system operators and enable more power delivery to electricity consumers through Jos Electricity Distribution Company.

Advertisement
Click to comment

Leave a Reply

Your email address will not be published. Required fields are marked *

RENEWED HOPE AGENDA

NRS: MANAGE YOUR TAXES ONLINE

Our Naira Our Pride

NNPC: WE ARE HIRING

THE RENEWED HOPE AGENDA

ADVERTISEMENT

PRESS RELEASE

Click to read full text


CAVEAT EMPTOR

Advertisement

CBN Advert

Click the link to visit
Advertisement
Advertisement
Advertisement

Happy New Year

Facebook

Advertisement
Advertisement

Breaking News...