TCN Repairs, Energizes Faulty 30MVA 132/33KV Transformer In Oghara, Delta State

Published

on

TCN MD, Mohammed

The Transmission Company of Nigeria (TCN) has completed repairs of the 30MVA 132/33kV power transformer in its Oghara Transmission Substation, Delta State which developed fault on the 10th of May, 2018.

The power transformer which was installed by NDDC in September, 2016, was repaired and energized on September 29, 2019.

According to the General Manager (Public Affairs) Ndidi Mbah, after the 30MVA power transformer tripped on differential protection, investigations carried out on the transformer revealed that the Neutral Bushing of the transformer had lost its insulation and required replacement.

She explained that efforts to get replacement bushing anywhere in the system failed as TCN did not have this transformer brand elsewhere in its system.

She noted that spares were not also made available as part of the contract by Niger Delta Development Commission (NDDC).

“As last resort, TCN ordered for the transformer’s brand of bushing abroad, this was delivered and conveyed to Oghara Transmission Substation on September 21, 2018. Replacement of the bushing was carried out in-house by TCN engineers, after installation, filtration and testing of the transformer were duly carried out, before the transformer was restored to service in September, 2018,” she said.

By this repair, TCN said that it had fully resumed the transmission of bulk electricity to Benin Electricity Distribution Company (BEDC) through the Oghara Substation.

Consequently, she said that IBEDC is expected to stop load shedding and resume normal supply to Teaching Hospital and Oghara Township.

The statement revealed that the Oghara Transmission Substation is a 2x30MVA 132/33kV capacity substation constructed by NDDC and commissioned in March, 2015.

It would be recalled that barely one year after commissioning, the Neutral Bushing of the first 30MVA power transformer developed fault on the 19th of June, 2016.

The second one was however in service until it equally developed fault in 10th of May, 2018.

TCN assured that it had procured enough spares and have also commenced repairs on the other transformer.

TCN expressed gratitude to electricity consumers affected by the Oghara Substation Fault, for their patience during the period and pledged to continue to ensure prompt resolution to any fault on the nation’s transmission network.

Further, it assured that necessary steps for the fortification and standardization of substations, lines and major equipment all over the country have been taken.

Advertisement
Click to comment

Leave a Reply

Your email address will not be published. Required fields are marked *

FIRS – Dial *829#

Our Naira Our Pride

NNPC: WE ARE HIRING

THE RENEWED HOPE AGENDA

ADVERTISEMENT

PRESS RELEASE

Click to read full text


CAVEAT EMPTOR

Advertisement

CBN Advert

Click the link to visit
Advertisement
Advertisement
Advertisement

Happy New Year

Facebook

Advertisement
Advertisement

Breaking News...