Vandals Destroy TotalEnergies Pipeline, Forces Shutdown Of 504MW Alaoji Power Plant

Published

on

Following the activities of vandals which led to destruction of TotalEnergies Pipeline, the 504MW Alaoji Power plant has been shutdown to give room for the repairs of the affected parts.

A statement by the Niger Delta Power Holding Company (NDPHC) Head, Communication & Public Relations, Emmanuel Ojor, indicated that TotalEnergies EP Nigeria Limited has declared a Force Majeure Event resulting from its NOPL Line vandalization at KP41 on January 7, 2022. 

According to TotalEnergies EP Nigeria Limited in a letter to the Niger Delta Power Holding Company Limited (NDPHC), “NOPL pipeline was vandalized on 7th January 2022 at KP41 Alaoma Etche Cluster.

The Line Block Valve at KP38 was closed to isolate the sabotage point and depressurization of the line, this will affect gas supply to Alaoji (Power Plant) until further notice.  

As a result of this development, TotalEnergies EP Nigeria Limited stated that “Gas supply to Alaoji Power Plant was suspended due to this unfortunate event. Preliminary investigation to determine the extent of the damage is ongoing, and repair works shall commence as soon as feasible.”  

The Management of Niger Delta Power Holding Company (NDPHC) Limited regretted to announce the shutdown of 504MW Alaoji Power Plant on January 7, 2022.  

“Please recall that Omotosho NIPP was shut down last month when Nigeria Gas Company (NGC) due to system wide curtailment of all gas shippers (gas producers/off takers) by Nigeria Gas Company (NGC) “to forestall the imminent collapse of the gas grid.” NGC said at the time that the Trans-Forcardos Pipeline (TFP), belonging to NGC was breached on December 17, 2021.
 
“That breach led to the deferment of about 250MMscfd of gas from the Pipeline Network, a situation that brought the Network Pressure to abysmal levels, thereby triggering an emergency.  

“The curtailment impacted operations of Niger Delta Power Holding Company (NDPHC) Limited negatively with Omotosho NIPP being shut down and gas supply to GEREGU NIPP and Ihovbor NIPP also limited thus leading to part load or low generation from these available power plants”, NDPHC stated.  

The Management however assured customers that Alaoji Power Plant and others would resume power generation as soon as gas supply is restored. 